Borderlands line

Borderlands line
A Class 150 DMU on the Borderlands line near Bidston
Overview
Other name(s)
  • Bidston–Wrexham line
  • Wrexham–Bidston line
Native name
  • Llinell y Gororau
  • Lein y Gororau
  • Llinell Wrecsam–Bidston
StatusOpen to passenger and freight use
OwnerNetwork Rail
Locale
Termini
Connecting lines
Stations15, with Wrexham General and Shotton as interchanges with mainline services, and Bidston connecting with Merseyrail
Service
TypeHeavy rail
SystemNational Rail
Wales and Borders franchise
Operator(s)Transport for Wales
Rolling stock
Technical
Line length27 mi (43 km)
Number of tracksDouble track throughout except Wrexham General to Wrexham Central
Track gauge4 ft 8+12 in (1,435 mm) standard gauge
Route map

(Click to expand)[1]
Bidston Merseyrail
Bidston Sidings
Upton
Woodchurch (proposed)
Storeton
Heswall
Neston
Burton Point
England
Wales
border
Sealand Rifle Range Halt
Birkenhead Junction Golf Club Platform
 
Shotton Paper
Deeside Parkway (proposed)
Deeside Industrial Park
Chester Golf Club Halt
Hawarden Bridge
Shotton
North Wales Coast Line
Hawarden
Buckley
Castle Cement
Hope Exchange
Chester–Denbigh line
Penyffordd Sidings
Penyffordd
Hope
Caergwrle
Cefn-y-Bedd
Cegidog Viaduct
over River Cegidog
Gwersyllt
Gwersyllt Junction
WM&CQ Brymbo branch
Rhosddu Halt
Wrexham General
Wrexham Central

The Borderlands line (Welsh: Llinell y Gororau[2] or Lein y Gororau), also known as the Bidston–Wrexham or Wrexham–Bidston[i] line, is a railway line between Bidston on the Wirral Peninsula in England and Wrexham Central in the north-east of Wales. Passenger train services are part of the Wales & Borders franchise and are operated by Transport for Wales Rail. The line connects to the Merseyrail network at Bidston, the North Wales Coast Line at Shotton and the Shrewsbury–Chester line at Wrexham General. Parts of the line in Wales are used by freight trains, serving Deeside Industrial Park and the Hanson Cement works to the south of Buckley.

The line is part of Transport for Wales' North Wales Metro improvement programme and is also referred to in England as the Mid Wirral line,[3] as part of the line runs in the middle of the Wirral peninsula.

The line is operated by the Class 230[4] and the Class 197.[5]

There have been various proposals for the line to be fully or partially integrated with the electrified Merseyrail network to increase services towards Liverpool. Past proposals for electrification on the line were deemed unfeasible due to costs. The potential introduction of Merseyrail's Class 777 on the line could expand services on the line into Liverpool.

Operations

[edit]
Logo for the line displayed outside Wrexham General

Freight services

[edit]

The line is used by freight trains at its southern end in Wales, serving Deeside Industrial Park and the Hanson Cement works south of Buckley. Amongst the biggest users of freight was the Shotton steelworks which received imported iron ore from Birkenhead's Bidston Dock, until the closure of the steelworks in 1980.[6][7]

Passenger rail franchise

[edit]

Upon privatisation, passenger services were transferred from Regional Railways to North West Trains, later known as First North Western. In 2003, a review led to the creation of the All-Wales Franchise, meaning services were transferred to Wales & Borders Trains. Arriva Trains Wales succeeded Wales & Borders on 8 December 2003, and operated all passenger services on the line until October 2018. KeolisAmey Wales (trading as Transport for Wales) then began its franchise until February 2021, when publicly-owned Transport for Wales Rail took over. Potential electrification plans could see the line transfer to Merseyrail.[8]

Passenger services

[edit]

Transport for Wales is currently the only passenger train operator on the line. There are proposals for Merseyrail to fully or partly operate on the line.

In their December 2021 to May 2022 timetable,[9] Transport for Wales operated 1 train per hour (tph) Monday to Saturday, and on Sundays services were mainly hourly with some every 1 hour and 30 minutes. Not all services terminated at Wrexham Central; some terminated at Wrexham General to enable cab cleaning, service turnaround time, or recovering delays.[10] In the May to December 2022 timetable,[11] the frequency remained at mainly 1tph, with all but the first morning and last evening service on weekdays, and two morning and two evening services on Sundays, stopping at Wrexham Central.

There are three interchange stations on the line, connecting to other railway lines and services. They are (north to south):

Holders of the Transport for Wales Concessionary Travel Pass can travel free along part of the line, from Wrexham Central to Hawarden Bridge.[12] Holders of the Merseytravel Concessionary Travel Pass can travel free along the section of the line that runs through Merseyside, from Heswall to Bidston.

In December 2021, more than 500 people signed a Change.org petition calling for a direct service between Heswall and Liverpool.[13][14]

The line is designated as a community rail partnership.[15]

In Spring 2023, some services were suspended after Transport for Wales transferred trains to other parts of their network. In June 2023, Transport for Wales committed to improve services on the line, with Lee Waters, Welsh minister responsible for transport, apologising for the issues. Class 230s were introduced in April 2023, although they were not running on-time and experiencing "teething" problems.[16]

Recent service developments
[edit]

It was initially proposed in 2018, that Transport for Wales would double the line's frequency to 2tph, starting from December 2021,[10] using the newly-introduced Class 230 trains. In September 2021, this was delayed to May 2022.[10] In May 2022, the planned timetable with the increased service was revised with the additional services removed,[11] therefore any increase in frequency was scrapped for May 2022[17] and servuces remained largely unchanged from the existing timetable at roughly 1tph until December 2022.

In March 2021, Transport for Wales pledged to Flintshire councillors that the line's services would increase to 4tph and extend into Liverpool.[18][19] The line's ageing track and signalling would also be replaced to allow for faster and more frequent trains. TfW also pledged to upgrade the facilities at the "fairly basic" stations on the line.[18]

GB Railfreight (GBRf) operate freight trains to Hanson Cement near Penyffordd. GBRf formally objected to the increase in passenger train services on the line as it would conflict with the freight operator's new daytime freight traffic to and from Padeswood.[17][20] The operator claimed that the new freight service would block the northbound line between Penyffordd and Buckley for 30 minutes due to the splitting of trains into and out of the short sidings.[17][21]

Both TfW and GBRf have applied to the Office of Rail and Road (ORR) for use of capacity on the line.[17] Transport for Wales Rail was seeking additional rights to operate a 2tph service on the line.[21] Analysis by Network Rail taken in June 2020 concluded that a 2tph service could not be operated regularly in conjunction with freight services, therefore they would not support the awarding of access rights to TfW.[21] Local councillors in Wrexham and the Wrexham-Bidston Rail Users' Association voiced concerns that the conflicting applications could jeopardise the planned increase in frequency to 2tph.[22][23]

On 30 November 2022, the ORR approved TfW's 2tph passenger service increase.[24]

Infrastructure history

[edit]
Borderlands line diagram

The southern part of the line was built by the Wrexham, Mold and Connah's Quay Railway (WMCQR) in 1864 and the northern part by the North Wales and Liverpool Railway, a joint committee of the WMCQR and the Manchester, Sheffield and Lincolnshire Railway in 1896. The North Wales and Liverpool Railway northern terminus was at Bidston with the southern terminus at Hawarden Bridge[25] Both railways were acquired by the Great Central Railway on 1 January 1905.

Two Wirral stations on the line closed in the 1950s; Storeton in 1951 and Burton Point in 1955. No trace of the station at Storeton remains, yet Burton Point station is still almost entirely intact, the station buildings currently forming part of a garden centre.[26] Further south, the high level platforms of Hope Exchange closed in 1958.[27]

The northern terminal of the Borderlands Line has been at four stations at various times: Bidston, Birkenhead North, Birkenhead Park (briefly in the late 60s), New Brighton and Seacombe.[28][29]

Development

[edit]

The doubling of the journey frequency on the line is one of the aims of the Growth Track 360 group, a consortium of business, politicians and public sector leaders. The group aims to improve transport and create jobs in the North Wales, Merseyside and Cheshire area over the next 20 years.[30] In the 2017 Autumn budget, Chancellor Philip Hammond stated that part of the additional £1.2 billion funding Wales was receiving would be used to look into proposals to improve journey times on the line and developing a business case.[31]

In October 2019, Transport for Wales announced £280,000 had been allocated to revamp stations along the line in north Wales, Cheshire and Merseyside, as part of TfW's £194 million station improvement programme.[32][33]

Proposed new stations

[edit]

New stations at Deeside Industrial Park (to be called Deeside Parkway), Woodchurch and Beechwood have been proposed.[34] The route was mentioned in Merseytravel's proposed 30-year plan of 2014.

"New stations at Beechwood and Woodchurch in Birkenhead (the latter "would be around junction 3 of the M53, the Prenton/Oxton side") and Deeside Industrial Park. These changes would "Incorporate the line into the Merseyrail Wirral line to provide direct connectivity with Liverpool city centre."[35]

The draft of the Network Rail Welsh Route Study in March 2015 contained several suggestions for improving services on the line, including:.[36]

  • Replacing the High and Low levels at Shotton station with a dedicated interchange station, improving connectivity between the North Wales Coast Main Line & the Borderlands line
  • The removal of level crossings to improve line speed.

Proposed electrification

[edit]

There have been proposals for the full or partial electrification of the line since 1999 with participation of Merseytravel and the devolved institutions in Wales.[ii] Such electrification is usually intertwined with proposals for the full incorporation of the line into the electrified Merseyrail network, allowing for services from either Wrexham Central or partway along the line to travel all the way to Birkenhead and Liverpool Central.[34][37]

In 2008, a Network Rail study estimated the cost for third-rail electrification of the entire line to be £207 million.[38] To lower costs, Merseytravel suggested overhead-wire electrification as an alternative, bringing estimates down to £66 million. However, this would mean trains running between Wrexham and Liverpool would have to be compatible with both electric systems, therefore incompatible with the third-rail only trains in use at the time.[39][40][41]

There is political support to electrify the line from both Welsh and Merseyside authorities, but the responsibility of rail infrastructure lies with the UK Government's Department for Transport.[42] The Welsh Government aims to increase services between North Wales and Merseyside, in particular Wrexham and Deeside with Liverpool and Liverpool John Lennon Airport.[43] Whereas Merseyside authorities would like to increase services to stations on the line on the Wirral Peninsula in particular, as well as the rest of the line.

In 2016, a working group was set up to examine improving the line, including proposals to increase the frequency of trains on the line. It was hoped that an increase in the number of passengers would improve the case for electrification.[44][45]

Alternatives to electrification

[edit]

In 2017, Merseyside councillor Liam Robinson stated that passenger use on the line had increased 75% over the previous decade but electrification was still a long-term aspiration. He also stated that the new Class 777 rolling stock, which can operate on overhead wires, third rail or batteries was being procured for Merseyrail, and could run on the line. The Class 777 trains could extend the line into the Liverpool and Birkenhead tunnels and stations.[46]

Welsh Government minister, Lee Waters, revealed in April 2023 that Transport for Wales have a Memorandum of Understanding with the Liverpool City Region Combined Authority to work collaboratively to increase connectivity between the two regions.[47]

Rolling stock

[edit]

The line is traditionally operated with Class 150 DMUs.[48] Bi-modal battery electric diesel Class 230s for Transport for Wales entered passenger service on the line on 3 April 2023.[49][50] They were originally set to enter service in May 2022[iii][17] in conjunction with a possible increase in service frequency.[51][52][53] On 24 May 2022, Class 197s were tested on the line, despite being initially excluded.[54] On 1 July 2022, TfW announced that the Class 197s would be used on the line.[55][56][57] The long-delayed 230s had its staff training suspended following a battery-related incident in April 2022, TfW stated they had targeted a late 2022 introduction as they aimed to restart the 230s' staff training programme in August 2022.[58][59]

Battery trains

[edit]
British Rail Class 230 on test at Stourbridge Junction, were set to be introduced on the line by TfW

It had been proposed to use trains that receive energy from batteries and an electric pick-up on both unelectrified and electrified sections of the track. This would reduce the need for full line electrification.[36]

A trial of a converted Electrostar train using energy from overhead wires and batteries when on non-electrified sections of track was undertaken in January and February 2015 on the Mayflower line. The train travelled up to 60 miles on energy stored in the batteries also recharging the batteries via the overhead wires when on electrified track, at stations and via brake regeneration.[60] A month later in March 2015, the introduction of battery powered trains was proposed for the Borderlands line by Network Rail.[36]

The Network Rail document suggested that consideration had been given to electrification and to extending the terminus from Bidston further into Birkenhead for greater connectivity. However these options were expressed as offering low value for money. The document proposes that using battery powered rolling stock precluding full electrification of the line, provides a cheaper method of increasing connectivity and extending the service into the electrified Birkenhead and Liverpool sections of the Wirral line. From the document:

"In the longer term, potential deployment of rolling stock with the ability to operate on battery power for part of their journey may provide the ability in an affordable manner to improve the service offering between the Wrexham – Bidston route and Liverpool."[36]

Class 230

[edit]

It was announced in June 2018 that refurbished Class 230 trains, which use former London Underground D78 Stock train bogies and aluminium bodyshells with battery power plants and a diesel engine as a failsafe, were to be introduced between Wrexham and Bidston.[52][53] Initially hoped for a mid-2019,[61] then a December 2019[61] introduction, the trains were delivered by Vivarail to Transport for Wales in July 2020.[17][62] The trains were later passed for passenger use for a 2020 introduction, but delayed initially to May 2022.[51] In July 2021, one unit caught fire near Wrexham Central.[63] In April 2022, Transport for Wales stated it continued to aim for a May 2022 introduction,[17][23] but by mid-May, no Class 230 trains were introduced and the extra services planned to use Class 230s were later removed from the May 2022 timetable.[17][11] Transport for Wales states that earlier delays to the introduction of the new trains were due to (aside the COVID-19 pandemic) "technical issues" such as fires on some of the tested trains and battery-related issues (such as a battery-related "thermal" issue in April 2022) impacting staff training, with the sheer length of a pause in training meant staff would have to re-do training.[17][54][58] A social media interaction on Twitter resulted in Transport for Wales' Twitter manager stating that the trains are set to be introduced "in the next year" (2023).[17] Deeside.com and Wrexham.com, local news websites, stated there is speculation that Transport for Wales have bought or leased Class 150s from another train operating company for the planned increase in services on the line.[17]

The trains were scheduled to start operating on the line in May 2022, however, on 24 May 2022, the new Class 197s were spotted for compatibility testing on the line.[54] Class 197s were not announced to be on the Borderlands line prior to the missed May 2022 introduction of the Class 230s.[54] Class 197s were intended to only run long-distance services on the whole Wales & Borders network, which the Borderlands line does not interact with.[54]

On 4 July 2022, TfW admitted battery-related "thermal issues" were the cause of the train's delayed introduction. TfW stated they have largely rectified the problem. The pausing of the staff training programme for a prolonged period of time, due to the incident, has led to staff being required to redo training.[58] The class 230 trains were introduced in fare paying service in April 2023.[64]

Following their introduction, the trains by June 2023, were still not running to their timetabled times, experiencing "minor technical issues" and "teething" problems.[16][65] This was later stated to be due to pollen blocking engine filters.[66] Following the issues with the services, Mark Isherwood, North Wales MS, had called for an operator other than Transport for Wales to operate the line, criticising TfW's management of services on the line.[67]

There are aspirations to extend services from Bidston onto the Merseyrail Wirral Line taking trains into the Birkenhead and Liverpool underground sections.[68]

Alternative future trains

[edit]
A Class 197 at Llandudno Junction, on the North Wales Coast Line, north-west Wales in October 2021

Class 197s

[edit]

On 1 July 2022, Transport for Wales announced that the Class 197s would be operating on the line when they are eventually introduced to the wider Wales and Borders rail network.[55][56] The class were not initially announced to be operating on the line when they first entered testing in late 2021, with Transport for Wales stating, at the time, that the 230s would be the line's main rolling stock.[57] The Class 197s were spotted being tested on the line in May 2022,[54] after the initial deadline for the 230s' May introduction had passed when the May–December 2022 timetable commenced.[17][11]

Class 777 of Merseyrail, proposed for use on the line

Merseyrail trains

[edit]

The Liverpool City Region Combined Authority announced that trials of the seven battery electric multiple unit (BEMU) versions of their new Class 777 had shown that they were capable of travelling up to 20 miles (32 km) between charges.[69] Further trials by Stadler reached a range of 84 miles (135 km).[70] This would allow the line to be served without full electrification.

Notes

[edit]
  1. ^ Welsh: Llinell Wrecsam–Bidston, also stylised as Bidston to Wrexham or Wrexham to Bidston
  2. ^ National Assembly for Wales (now Senedd), Welsh Government and Transport for Wales
  3. ^ delayed from 2020 due to the COVID-19 pandemic

References

[edit]
  1. ^ "Borderlands Line Route" (PDF). Borderlands Line. Archived from the original (PDF) on 19 May 2014. Retrieved 9 June 2013.
  2. ^ "TfW Network Map" (PDF). Transport for Wales. Retrieved 8 December 2021.
  3. ^ Usage of the term "Mid Wirral line" or "Mid-Wirral line"
  4. ^ Longhorn, Danny (3 April 2023). "Wales' first hybrid train enters service on Borderlands Line". RailBusinessDaily. Retrieved 10 June 2024.
  5. ^ "Wrexham-Bidston line boosted with new Class 197 'made in Wales' trains". Deeside.com. Retrieved 10 June 2024.
  6. ^ "Events that shook North Wales: Closure of Shotton Steelworks". 21 July 2018.
  7. ^ "CAPACITY CRUNCH AT CHESTER". www.modernrailways.com. 22 June 2017.
  8. ^ "The Wrexham to Bidston railway (The Borderlands line): Electrification plans". Retrieved 17 February 2007.
  9. ^ Train Times – 12 December 2021 – 14 May 2022; Bidston (Birkenhead) – Wrexham Central (PDF). Transport for Wales. 2021.
  10. ^ a b c "Borderlands frequency increase deferred to May". www.modernrailways.com. 17 September 2021. Retrieved 16 May 2022.
  11. ^ a b c d Train Times – 15 May 2022 – 10 December 2022 – Bidston (Birkenhead) – Wrexham Central (PDF). Transport for Wales. 2022.
  12. ^ "Over-60 Rail Concessions | Transport for Wales".
  13. ^ "Hundreds call for direct line rail service from Heswall to Liverpool". Wirral Globe. 21 December 2021. Retrieved 17 May 2022.
  14. ^ Morgan, George (19 December 2021). "Hundreds sign petition for new train line to Liverpool". Liverpool Echo. Retrieved 17 May 2022.
  15. ^ "ACORP Summary map" (PDF). Association of Community Rail Partnerships. 28 July 2014. Archived from the original (PDF) on 18 November 2015. Retrieved 28 October 2015.
  16. ^ a b "Welsh Government commits to improve Wrexham-Bidston (Borderlands) line". RailAdvent. Retrieved 8 July 2023.
  17. ^ a b c d e f g h i j k l "Still no sign of TfW's new Class 230 trains after three years of delays". Wrexham.com. Retrieved 16 May 2022.
  18. ^ a b "Four trains an hour pledge for Wrexham-Bidston rail line". BBC News. 10 March 2021. Retrieved 16 May 2022.
  19. ^ "Major upgrades on cards for train services on 'Cinderella Route' from Wrexham to Bidston". The Leader. 9 March 2021. Retrieved 16 May 2022.
  20. ^ "After three years of delays, there is still no sign of TfW's new Class 230 trains". Deeside.com. Retrieved 16 May 2022.
  21. ^ a b c Hickman, Claire (21 December 2021). Proposed amendment to the Track Access Contract between Network Rail Infrastructure Limited & Transport for Wales Rail Limited (TfWRL) Under Section 22a of the Railways Act 1993 (PDF). Network Rail.
  22. ^ "Concerns raised over train service between Wrexham and Bidston". The Leader. 25 February 2022. Retrieved 16 May 2022.
  23. ^ a b "New trains could be operating through Flintshire from May but no green light for two an hour service". Deeside.com. Retrieved 17 May 2022.
  24. ^ "Regulator gives green light for two trains per hour on Wrexham to Bidston railway line". Deeside.com. Retrieved 30 November 2022.
  25. ^ Mitchell, Vic; Smith, Keith (2013). Wrexham to New Brighton. West Sussex: Middleton Press. map XXXIII. ISBN 9781908174475. OCLC 859543196.
  26. ^ "Station Name: BURTON POINT". Disused Stations. Retrieved 9 June 2013.
  27. ^ "Station Name: Hope High Level Station". Disused Stations. Retrieved 11 February 2016.
  28. ^ "Disused Stations: Seacombe Station". www.disused-stations.org.uk. Retrieved 20 July 2021.
  29. ^ "Disused Stations: Railways at Bidston". www.disused-stations.org.uk. Retrieved 20 July 2021.
  30. ^ "About Growth Track 360". www.growthtrack360.com. Growth Track 360. Retrieved 1 December 2016.
  31. ^ "Budget gives extra £1.2bn to Wales". BBC News. 22 November 2017. Retrieved 22 November 2017.
  32. ^ "Borderlands line rail stations set for £280k revamp". BBC News. 24 October 2019. Retrieved 16 May 2022.
  33. ^ "£194m railway stations upgrade revealed by Transport for Wales". BBC News. 16 September 2019. Retrieved 16 May 2022.
  34. ^ a b "Merseytravel's plans to carry out further studies into the electrification of the railway track". Wirral Globe. 29 September 1999. Retrieved 16 February 2016.
  35. ^ Shennan, Paddy (28 August 2014). "Merseytravel plan to open or reopen host of new stations". Liverpool Echo. Retrieved 30 August 2014.
  36. ^ a b c d "Welsh Route Study – Draft for Consultation". Network Rail. Archived from the original on 12 October 2016. Retrieved 6 March 2015.
  37. ^ "The Wrexham to Bidston railway (The Borderlands line): Electrification plans". Retrieved 9 June 2013.
  38. ^ "Merseytravel fury over £207m price tag for Bidston-Wrexham rail link". Wirral News. Liverpool. 5 November 2008. Archived from the original on 8 January 2009.
  39. ^ "The Wrexham to Bidston railway (The Borderlands line): Electrification plans". Penmorfa. Retrieved 17 April 2015.
  40. ^ "The Wrexham to Bidston railway (The Borderlands line): Electrification plans". Penmorfa. Retrieved 17 February 2007.
  41. ^ "Network RUS Electrification" (PDF). October 2009. Archived from the original (PDF) on 12 October 2014. Retrieved 20 October 2013.
  42. ^ Hughes, Owen (29 January 2013). "Plea for £2bn windfall for Wales after high speed rail announcement". Daily Post. Retrieved 9 June 2013.
  43. ^ "Progress on Liverpool-North Wales rail link". North Wales Weekly News. Conwy. 25 October 2012.[permanent dead link]
  44. ^ "Loop line renewal is 'short-term pain worth long-term gain of rail boost' writes MerseyTravel chief". Wirral Globe. 16 November 2016. Retrieved 1 December 2016.
  45. ^ "Agenda item – Rail Schemes Development and Delivery". Merseytravel. 3 November 2016. Archived from the original on 2 December 2016. Retrieved 1 December 2016.
  46. ^ "The Halton Curve: Small piece of track, big rail ambitions". www.railtechnologymagazine.com. Retrieved 9 September 2017.
  47. ^ Ash, Emily (4 April 2023). "Talks are ongoing for regular direct trains from Wrexham to Liverpool". The Leader. Retrieved 10 April 2023.
  48. ^ "No new trains on Wrexham Bidston line this year – Current trains to be moved to South Wales and replaced with … 'Scuds'". Deeside.com. Retrieved 1 July 2022.
  49. ^ "Delayed Class 230 train finally begins passenger service on Wrexham – Bidston line". Wrexham.com. Retrieved 3 April 2023.
  50. ^ "Wales' first battery-electric train enters service on Borderlands Line". RailAdvent. Retrieved 3 April 2023.
  51. ^ a b "Vivarail certifies UK's first battery-powered train | RailTech.com". RailTech.com | Online News for the Railway Industry. 27 January 2020. Retrieved 20 July 2021.
  52. ^ a b "What's Happening in North Wales | Transport for Wales". trc.cymru. 17 May 2021. Retrieved 20 July 2021.
  53. ^ a b "Refurbed London Underground trains for Wrexham to Bidston service + Keolis UK to move HQ to Wales". Wrexham.com. Retrieved 20 July 2021.
  54. ^ a b c d e f "New train type spotted on Wrexham to Bidston line being tested to see if "capable of operating" on route". Wrexham.com. Retrieved 25 May 2022.
  55. ^ a b "New Transport for Wales confirm the new Class 197 trains will operate on the Wrexham to Bidston line". Deeside.com. Retrieved 1 July 2022.
  56. ^ a b Hughes, Owen (30 June 2022). "New Transport for Wales trains unveiled – when and where they will be running". North Wales Live. Retrieved 1 July 2022.
  57. ^ a b Hughes, Owen (1 December 2021). "New Transport for Wales carriages filmed rolling into town – this is when and where they'll be used". North Wales Live. Retrieved 1 July 2022.
  58. ^ a b c "TfW opens up on 'thermal incidents' delaying introduction of recycled tube trains on Wrexham to Bidston line". Wrexham.com. Retrieved 4 July 2022.
  59. ^ "Testing of TfW's troubled Class 230 trains back underway following three month suspension". Wrexham.com. Retrieved 20 August 2022.
  60. ^ Clinnick, Richard (13 January 2015). "Battery-powered Electrostar enters traffic". Rail. Retrieved 17 April 2015.
  61. ^ a b "New trains set to come into service on Wrexham to Bidston line in December". Deeside.com. Retrieved 17 May 2022.
  62. ^ "New Wrexham to Bidston hybrid trains first journey to North Wales is a 'Champagne moment' for manufacturer". Deeside.com. Retrieved 17 May 2022.
  63. ^ "Firefighters called deal with 'small fire' on new Class 230 trains due to come into service later this year". Deeside.com. Retrieved 4 July 2022.
  64. ^ "Much delayed Class 230 train enters passenger service on Wrexham – Bidston line for first time". Deeside.com.
  65. ^ "New hybrid trains in Wales experience 'minor technical issues' and vandalism". The Leader. 11 April 2023. Retrieved 8 July 2023.
  66. ^ "Blooming Problem: Pollen blamed for causing technical issues with new Borderlands Line trains". Deeside.com. Retrieved 15 July 2023.
  67. ^ "Calls made for Wrexham-Bidston rail line to be transferred to another operator". The Leader. 18 May 2023. Retrieved 8 July 2023.
  68. ^ "Wrexham to Bidston railway line will be 'greatly improved' under new plans". The Leader. 7 June 2018. Retrieved 20 July 2021.
  69. ^ "Battery breakthrough will see Merseyrail network extended". 21 July 2021.
  70. ^ "New Merseyrail train runs 135km on battery". 19 December 2022.
[edit]