Plomin Power Station

Plomin Power station
Plomin Power Station in 2007, with two steam tubine units.
Map
Official nameTermoelektrana Plomin
CountryCroatia
LocationPlomin, Istria County
Coordinates45°08′11″N 14°09′54″E / 45.13639°N 14.16500°E / 45.13639; 14.16500
StatusOperational
Commission date1970
OwnerHrvatska elektroprivreda
Thermal power station
Primary fuelStone coal
Power generation
Units operational1 x 199 MW - Plomin B
Make and modelDolmer - Plomin A
Končar - Plomin B
Units decommissioned1 x 120 MW - Plomin A
Nameplate capacity199 MWh
Annual net output1,459.1 GWh
External links
CommonsRelated media on Commons

Plomin Power Station (Croatian: Termoelektrana Plomin) is a coal-fired power station near Plomin, Croatia. As of 2021, its production corresponded to 7.6% of Croatia's electricity needs.[1]

The power plant consists of two boiler units: TE Plomin A, built in 1969 and shut down in 2018 and TE Plomin B, built in 2000. Both are operated by Hrvatska elektroprivreda, and the latter was co-owned with RWE Power AG.[2] On 28 May 2015, the contract signed by the two parties in 1996 expired, thereby transferring the thermal power plant into 100 percent ownership of HEP. They generate a total of 199 megawatt. In 2021 their total output was 1,459.1 GWh.[1]

In 2011, the reconstruction of the Plomin A Power Station was proposed for a more efficient and safer functioning. The capacity of the new station, named Plomin C, will be of 500 MW instead the 125 MW of the old one, a fact that created ambiguities as it was mostly viewed as a new project rather than a reconstruction of the Plomin A plant. As a result, the Plomin Power Station capacity will increase from 335 MW to 710 MW. The upper limit of 335 MW was planned to be the maximum to be allowed at Plomin plant, an increase in capacity being possible only using gas rather than coal. However, the Croatian government supported the project, viewing it as “rational and cost effective”.[3]

Plomin Power Station has a 340 metres (1,120 ft) tall chimney, which is the tallest constructed structure in Croatia.

Components of the Plomin Power Station

[edit]

Plomin A

[edit]

Plomin A power station was built in 1969. It represents one of the two existing power plants at Plomin Power Station from Istria, Croatia. The capacity of Plomin A is 120 MW and it is operated by Hrvatska elektroprivreda.

In 2011, the reconstruction and modernization of the plant was proposed and its incorporation into Plomin C power station.[2] The Block A 125 MW production unit was completed and put into operation in 1970. As of January 1, 2018, the Decision on Unified Conditions for Environmental Protection (Environmental Permit) ceased to be valid, so Block A is an unavailable production unit until further notice.[4]

Plomin B

[edit]

The production unit Block B (TE Plomin 2) with a capacity of 210 MW was built and put into commercial operation in 2000. The plant was built under the company TE Plomin d.o.o as joint venture by HEP and RWE. On August 1, 2017, the company TE Plomin d.o.o. was merged with HEP d.d., and operations continue within the framework of the company HEP - Proizvodnja d.o.o.[4]

Block B has been equipped with a flue gas desulfurization plant since 2000. The device for removing nitrogen oxides from flue gases was completed and put into operation in 2017. With the modernization of the low-pressure part of the turbine and the capital overhaul activities on other parts of the system carried out in 2017, an improvement was achieved in the internal degree of utilization of the turbine, which increased the nominal power of the turbo-unit to 217 MW.[4]

The connection of Block B to the electric power system was achieved with a 220/110 kV switchgear.[4]

Plomin C

[edit]

Plomin C was a 500 megawatt (MW) coal power plant project to be built as a third unit of the Plomin Power Plant. The project was operated by the Hrvatska elektroprivreda (HEP) and it was presented as a reconstruction of the Plomin A Power Plant, even though its capacity is planned to be four times bigger than the previous one (125 MW). This has generated a lot of discussions on the legality and sustainability of the project among local and international groups, as well as from local officials.[5] The value of the investment is of EUR 800 million. The project was planned to start in 2013 and end in 2017 or 2018,[6] but eventually was cancelled in 2016.[5]

Description of the project

[edit]

The purpose of the project is to reconstruct Plomin A Power Plant and to assure a safe long-term source of energy, as well as to decrease the dependence of the country on the imported energy. Croatia being a country that imports more than 30% of the consumed energy.[7] Environmental NGOs affirm that, on the other side, it will increase the import of coal as the country does not have domestic resources, thus maintaining the external dependence.[5] HEP defended by saying that unlike gas and oil, coal comes from politically stable countries, mainly OECD, thus the supply for this raw material can be easily assured. Additionally, the project is presented as improving the environmental conditions on the region as the old Plomin A Power Plant will be closed and C will be opened. The construction of the new station will be realized in accordance with the guidance of the European Union so that the “Best Available Techniques” (BAT) are used. The BAT represent the most advanced and efficient methods that aim to reduce to the maximum the emissions and the environmental damage caused by power plants. Furthermore, HEP classifies Plomin C as a “near zero emission” power plant.[8] However, according to estimates, Plomin C will emit 2.644 million tonnes carbon dioxide equivalent.[5]

[edit]

One of the first phases of the Plomin C project was that it had to be accepted by the Croatian government. Due to the necessity of additional energy sources, Ministry of Spatial Planning and Construction approved HEP's Environmental Impact Assessment of the project in the middle of June, 2012. At the same time, the Environment and Nature Protection Minister, Mihael Zmajlovic, said that opting for coal instead of other raw materials was a „more rational and cost effective” way of operating the Plomin C. The newest technologies that would be used in the construction of the plant should assure that the environmental damage is minimal, pointed out the Minister.[9] The neighbor country, Slovenia was also consulted on the early age of planning of the Plomin C that was expected to have environmental impact not only on Croatia, but on the whole region. After continuous consultations with the specialized institutions, the Slovenian Ministry of Agriculture and Environment concluded that the project will not have significant effects on the environment and agreed on the construction of the plant.[10]

Hunton & Williams, a legal consultancy company, was hired by HEP to advise on international tender for the design, construction and operation of the power plant.[11]

Potential investors

[edit]

As RWE the investor in the Plomin B did not express interest in joining this project, HEP was looking for a partner interested in Plomin C coal-based power plant.[12] RWE explained the decision by their current capital constraint, as well as adjustment of the company's strategy related to the composition of the European power plant portfolio. However, RWE said that it will support the project from its position of shareholder of Plomin B. By 14 September 2012, the date of application deadline, seven companies expressed their interest in Plomin C.[13] However, HEP short-listed only four companies, which were asked to submit their bidding offers by the end of 2012 year. The short-listed candidates are:

The selection was planned to end at the beginning of the second quarter of 2013.[14]

Zelena Akcija/Green Action sent an awareness letter to the four companies, informing them regarding the economic and environmental negative effects the project may have and the locals opposition against its construction.[15]

Environmental issues

[edit]

Zelena Akcija (Friends of the Earth Croatia) and Green Istria, supported by locals as well, submitted a legal appeal to the Administrative Court in Rijeka on October 29, 2012, against the Ministry of Environmental Protection to challenge the environmental permit that was approved by them for the construction of the Plomin C Thermal Power Plant. They demanded to stop any further activities related to the project progress until the Court comes up with a decision.

The main reasons brought by the appealing party were the high CO2 emissions that will lead to worsening of the population health in the region as well as global warming effect and increased dependence on the imported coal. Furthermore, it will not allow Croatia to meet the conditions imposed by EU regarding the decrease of greenhouse gas emissions by 2050. This may affect even the economic side of the project as it may lead to the purchase of additional greenhouse gas emissions credits under the European Union Emissions Trading Scheme.[16] Prof.dr.sc Enco Tireli, a local expert, who worked for HEP for more than 20 years and was also construction manager for Plomin B, confirmed the fact that the project will not be profitable due to the additional payment for CO2 credits. According to EU goals, Croatia's total emissions will be in the range between 1.566 and 6.264 million tonnes Carbon dioxide equivalent (CO2eq) annually, while only Plomin C would emit 2.644 million tonnes CO2eq. Thus, there will be no reserves of CO2 emissions left for other sectors as industry and transportation.[17]

Zelena Akcija and Green Istria invoked that the assessment done by the Ministry did not consider in depth all the implications of the project on the human health and wellbeing.[18] Also, Dusica Radojic, the President of Green Istria, pointed out that "the plans to build Plomin C are in conflict with the Istria County Spatial Plan, which clearly defines that any new unit at the site cannot exceed 125 MW and must run on gas, not coal”.[16] The two associations stressed that “the consequences of such irresponsible approach will be supported by the local population, and the economic damages will have to be covered from the taxes paid by all citizens of Croatia”. Zelena Akcija and Green Istria hope that the Court will consider their arguments and cancel the environmental permit allowing the construction of the Plomin C coal power plant.[18]

See also

[edit]

References

[edit]
  1. ^ a b "Energija u Hrvatskoj 2021" (PDF). Energetski institut Hrvoje Požar (in Croatian and English). Ministry of Economy and Sustainable Development, Republic of Croatia. ISSN 1848-1787. Retrieved 2 November 2023.
  2. ^ a b . TE Plomin Archived 2013-04-04 at the Wayback Machine, Official site of HEP Proizvodnja
  3. ^ Coal-based Plomin power plant more rational, cost-effective[permanent dead link], Daily tportal website
  4. ^ a b c d "TE Plomin". HEP Proizvodnja (in Croatian). Retrieved 4 November 2023.
  5. ^ a b c d Plomin coal power plant, Croatia, CEE Bankwatch Network.
  6. ^ Cacic believes that new Plomin power plant will be finished in 2017, South East Europe Business Portal
  7. ^ Six bidders interested in Croatia's coal power plant, Reuters website
  8. ^ Reconstruction of TPP Plomin, Croatia, South-East European Industrial Market - issue 3/2012, September
  9. ^ Coal-based Plomin power plant more rational, cost-effective[permanent dead link], Daily tportal
  10. ^ Slovenia Agrees to Croatia Power Plant Plan, BalkanInsight webpage, August 10, 2012
  11. ^ Hunton & Williams Advises on €800m Power Plant in Croatia, Hunton & Williams website, August 17, 2012
  12. ^ Coal-based Plomin power plant more rational, cost-effective[permanent dead link], Daily tportal, April 13, 2013
  13. ^ Reconstruction of TPP Plomin, Croatia, South-East European Industrial Market - issue 3/2012, September
  14. ^ HEP short-lists four companies for Plomin C thermal power plant, Hrvatsko Izdanje - Dalje, September 28, 2012
  15. ^ Letters to companies shortlisted to bid for the Plomin coal power plant, CEE BankWatch Network, November 8, 2012
  16. ^ a b Croatian green groups mount legal challenge on "Plomin C" coal power plant, Zelena Akcija - Friends of the Earth, Croatia Website, November 29, 2012
  17. ^ Plomin coal power plant, Croatia, CEE BankWatch Network
  18. ^ a b Croatian Green Groups Filed Lawsuit against Environment Ministry over Plomin C TPP Permit, One World Platform for SouthEast Europe, October 31, 2012
[edit]