Confederation Line

Confederation Line

Overview
OwnerCity of Ottawa
Line number1
LocaleOttawa, Ontario
Stations13
WebsiteConfederation Line (Line 1)
Service
TypeLight rail
SystemO-Train
Operator(s)OC Transpo
Depot(s)Belfast Yard
Rolling stockAlstom Citadis Spirit
Daily ridership159,000 (avg. weekday, Q4 2019)[1]
History
OpenedSeptember 14, 2019; 5 years ago (2019-09-14)[2]
Technical
Line length12.5 km (7.8 mi)
CharacterAt-grade, underground
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification1,500 V DC from overhead catenary
Operating speed25–80 km/h (16–50 mph)
SignallingThales SelTrac CBTC
Route map

Stage 2 (2025)
Trim
Place d'Orléans
Convent Glen
Jeanne d'Arc
Montréal
Blair
Cyrville
St. Laurent
Belfast Yards
Maintenance Facility
Tremblay
Hurdman
Lees
uOttawa
Rideau
Parliament
Lyon
Pimisi
Bayview
Tunney's Pasture
Stage 2 (2027)
Westboro
Kichi Zìbì
Sherbourne
New Orchard
Lincoln Fields
Iris
Algonquin
Queensview
Pinecrest
Bayshore
Moodie

The Confederation Line (French: Ligne de la Confédération), also called O-Train Line 1 (French: Ligne 1 de l'O-Train),[3] is a light rail line operated by OC Transpo in Ottawa, Ontario, Canada, as part of the city's O-Train light rail system. It opened on September 14, 2019, and is O-Train's second line. It operates on an east–west route, with a segment under Queen Street in the downtown core, complementing the north–south Trillium Line that operates to the west of the downtown core.[4] Using light rail rolling stock and technology (e.g. pantograph electrical pickup from overhead catenary rather than a third rail), the Confederation Line is completely grade separated.

The project was approved by the Ottawa City Council and the contract was awarded in December 2012.[5] Construction began in 2013.[6] At a cost of just over CA$2.1 billion, the first stage of the line was the largest infrastructure project awarded in the history of the city before being surpassed by the Stage 2 extension of the line, which will cost $4.66 billion.[7][8][9]

History

[edit]
Completed Confederation Line tracks in August 2017

The line was approved unanimously by the City Council on December 19, 2012, after many years of debate on a rapid transit network for the city. It represents the initial phase of the network and will be implemented through a 30-year Design-Build-Finance-Maintenance agreement with the Rideau Transit Group.[10] It is operated by Alstom Citadis Spirit light rail vehicles.

On June 8, 2016, a sinkhole opened in the middle of Rideau Street near its intersection with Sussex Drive, 25 metres (82 ft) above the LRT tunnel construction, swallowing three lanes of the street and a parked van. The collapse forced evacuation of the Rideau Centre and the closing of a number of local streets and businesses; no one was injured or killed, but the nearly-completed tunnel was flooded, submerging a roadheader. Repairs were completed,[11] and the city was cleared of any wrong-doing.[12]

Testing of the line's rolling stock began in late 2016, and was planned to continue through most of the following year before the line was expected to achieve revenue service availability on May 24, 2018, followed by testing, acceptance, and opening of the line to the public.[13] When the May 2018 deadline could not be achieved, it was announced the line would open to the public in November 2018.[14][15] In September 2018, it was announced that the line would not open in November 2018 and would instead open in early 2019. In March 2019, this was pushed back to sometime between April and June 2019. In May 2019, the opening of the line was again delayed, until the third quarter of 2019, due to concerns about train operations.[16] Rideau Transit Group failed to complete testing and hand over the system by the revised deadline of August 16, 2019, the fourth time RTG had not met a deadline it had revised with the city.[17] OC Transpo announced on August 23, 2019, that the testing had been completed by RTG and the Confederation Line would open to the public on September 14, 2019.[18]

On March 10, 2020, Ottawa City Council issued a notice of default to RTG, listing the flaws and problems with the line and its operation.[19] Among the cited issues were a shortage of trains during rush hour, a maintenance facility fire, inadequate heating of train operator cars, and vehicle parts coming loose, the latter causing damage to transponders.[19]

On November 30, 2022, a public inquiry led by Justice William Hourigan issued a report criticizing both city politicians as well as the Rideau Transit Group consortium for problems in building and implementing the Confederation Line. Hourigan found that project deadlines were unrealistic with unachievable dates, and that information about testing problems was disclosed neither to city council (other than to then-mayor Jim Watson) nor to the public. Hourigan also made 103 recommendations to fix problems, including a recommendation that the province investigate how to develop skills and capabilities to deliver large municipal projects.[20]

Route and stations

[edit]

Route

[edit]

The Confederation Line runs from Tunney's Pasture station in the west to Blair station in the east, a distance of 12.5 kilometres (7.8 mi) including a 2.5-kilometre (1.6 mi) tunnel running under Queen Street in the central business district, including under the Rideau Canal.[7] The line connects to the existing Transitway at both ends, and to the O-Train Trillium Line at Bayview station.[21]

With complete grade separation, travel time from one end to another is less than 25 minutes.[22] Train frequency is every 5 minutes or better during peak hours and every 15 minutes or better after 11PM (except Sunday). The hours of operation for the Confederation Line are:[23]

  • Monday to Thursday: 5 am to 1 am
  • Friday: 5 am to 2 am
  • Saturday: 6 am to 2 am
  • Sunday: 8 am to 11 pm

Stations

[edit]

There are 13 stations in Stage 1 of the project. The three downtown subway stations have 120-metre (390 ft) platforms; the remainder are 90 metres (300 ft) with provisions for future expansion.

All stations display an illuminated red "O" at the entrance. Every station has fare vending machines selling Presto cards, single-ride tickets, day passes, family passes and multi-day passes; vending machines accept cash, debit cards and credit cards. Stations have an information phone as well as emergency phones for those requiring assistance; vending machines also provide a video chat feature. Access through the fare gates to station platforms is via Presto card, U-Pass, STO Multi card, barcoded ticket, barcoded bus transfer, mobile wallet, or bank card. All 13 Stage 1 stations have elevators, and nine have escalators. Station stairways have a channel for passengers to push a bicycle. Four of the 13 stations have public washrooms.[23]

The four major transfer stations—Blair, Hurdman, Bayview, and Tunney's Pasture—have a fare-paid area so that passengers transferring between bus and O-Train, or between the Confederation and Trillium lines, do not need to go through fare gates.uOttawa, Tremblay and Cyrville stations do not have nearby connecting buses. Lyon is the major hub for STO (Société de transport de l'Outaouais) buses connecting with OC Transpo services.[23]

Station Notes
Blair Connects with the East Transitway to Orleans. Serves the Gloucester City Centre shopping complex.
Cyrville Transitway station demolished and rebuilt to handle LRT in 2015. Serves the Ottawa CANEX (for military personnel and families).
St. Laurent Integrates with the St. Laurent Shopping Centre and connects to east end bus routes
Tremblay Connects with Via Rail inter-regional services at Ottawa station. A pedestrian bridge connects to Raymond Chabot Grant Thornton Park north of the Queensway. Also serves the Ottawa Trainyards shopping complex.
Hurdman Connects to the Southeast Transitway to south Ottawa
Lees Serves existing high-density residential buildings and the University of Ottawa Lees Campus.
uOttawa Serves the University of Ottawa and the Sandy Hill district. Replaces the previous Campus station.
Rideau Located under Rideau Street and integrated with the Rideau Centre. Replaces the existing Mackenzie King station and will be a major transfer station, providing transfers between the Confederation Line and the city's urban bus routes to the east (Montreal Road) and south (Bank Street). Serves the ByWard Market and Lower Town districts.
Parliament Located under Queen Street, replacing the Bank and Metcalfe stations. Connects to the Sun Life Centre and Heritage Place. Serves the northeast area of Centretown, including Parliament Hill and the National Arts Centre.
Lyon Located under Queen Street, replacing the Bay and Kent stations. Integrated with Place de Ville's underground concourse and a future Claridge residential development. Serves the northwest area of Centretown.
Pimisi Located in LeBreton Flats under the Booth Street bridge. Connects with Gatineau buses. Serves the Chinatown district, and is a short walk from Little Italy.
Bayview Connects with the north–south Trillium Line to south Ottawa. Serves the east end of the Hintonburg district and the west end of Chinatown.
Tunney's Pasture Connects with the West Transitway towards Barrhaven and Kanata. Serves the Wellington Street West district, including the western part of Hintonburg, and the Tunney's Pasture federal government complex.

Design issues

[edit]

Station design concerns have been raised; shortcomings identified include steps that are slippery when wet, which have resulted in passenger injuries.[24]

Future stations

[edit]
Station Notes
Stage 2 West
Westboro Will replace the existing Transitway station. Serves high-density residential and Westboro Village
Kichi Zìbì Will replace Dominion station. The station will be renamed Kichi Zìbì to better associate with the region's Algonquin heritage, the nearby Kitchissippi lookout and the City ward of the same name
Sherbourne New station will be below-grade, built as part of a cut-and-cover tunnel along the Byron Linear Tramway Park at Sherbourne Road
New Orchard New station will be below-grade, built as part of a cut-and-cover tunnel along the Byron Linear Tramway Park near New Orchard Avenue
Lincoln Fields Will replace the existing Transitway station. This station will be a major transfer point between the Algonquin (Line 1) and Moodie (Line 3) branches of the Confederation Line. It will include a fare-paid transfer zone as well as public washrooms.
Stage 2 West, Moodie Branch (Line 3)
Queensview Will be located near OC Transpo's Pinecrest garage between Queensview drive and the 417. A pedestrian bridge across the 417 is also being constructed to directly link to the station; although it will be completed before the LRT is operational, it will not be open to the public until the beginning of train service.
Pinecrest Will be located just west of Pinecrest Road and south of the existing Transitway station
Bayshore Will replace the existing Transitway station
Moodie Will replace the newly built Transitway station. A new maintenance and storage facility will be built beyond this station on the west side of Moodie Drive
Stage 2 West, Algonquin Branch (Line 1)
Iris Will replace the existing Transitway station
Algonquin Will replace the temporary Baseline station. The station will be renamed to Algonquin to better associate with the nearby Algonquin College campus. It will be a major transfer station for passengers riding south to Barrhaven, and will include a fare-paid transfer zone as well as public washrooms. An elevated pedestrian bridge is also being constructed to link the main station building with the second floor of Algonquin College's ACCE Building.
Stage 2 East
Montréal Will replace existing at-grade Transitway request stops and be built across Montreal Road in a newly constructed and widened Regional Road 174 overpass
Jeanne d'Arc Will replace the existing station and be built in the median of Highway 174 below Jeanne d'Arc Boulevard
Convent Glen New station will be built in the median of the 174 below Orléans Boulevard
Place d'Orléans Will replace existing Transitway station and be built in the median of the 174 and connect to the existing pedestrian bridge to connect to the Park and Ride and the Place d'Orleans Shopping Centre. This will be a major transfer station for riders living in Orléans and it will include a fare-paid transfer zone, with an additional pedestrian overpass constructed to provide direct between the bus and train platforms in the zone. It will also include public washrooms.
Trim Will be located in the median of the 174 and connect to the existing park-and-ride south of the 174 via a new pedestrian bridge. In the longer term, there are plans to construct an additional pedestrian bridge to link the station with the communities north of the 174.

Long-term expansion plans

[edit]
Station[25] Notes
Wesley Clover Parks A future side platform station is protected along the guideway being constructed for the Stage 2 West expansion, west of the terminus at Moodie station and in close proximity to the Moodie Yard LMSF. If constructed, it would be used for special events only at Wesley Clover Parks on the other side of Corkstown Road.
Gloucester High School / Trillium Park A future side platform station is protected in the vicinity of Gloucester High School and Trillium Park, just east of Blair station. This would serve nearby residential communities as well as provide a more direct link to the newly built shopping centre which includes a Costco Wholesale.
Orléans Town Centre A future side platform station is protected in the vicinity of the Orléans Centrum shopping district. It would be located in the median of Regional Road 174 and would include some form of pedestrian bridge connecting the station with the surrounding communities across the 174.
Tenth Line Road A future side platform station is protected at Tenth Line Road. It would be located in the median of Regional Road 174 underneath the Tenth Line Road overpass, not dissimilar in nature to Stage 2 East's Jeanne d'Arc and Convent Glen stations.

Rolling stock

[edit]

The winning consortium for the project, RTG, awarded Alstom a contract to provide 34 Citadis Spirit LRVs.[21] It was the company's first order for modern light rail vehicles in North America, competing directly with similar models such as the Siemens S70 (which was originally ordered for the original extension plan for the Trillium Line but was later cancelled). Derived from the earlier Citadis Dualis tram-train used in Europe, they were manufactured in Alstom's plant in Hornell, New York, with final assembly taking place at Belfast Yard in Ottawa.[26][27] The top speed of the vehicles is 105 kilometres per hour (65 mph), though the operating speed on the urban parts of the line are 80 kilometres per hour (50 mph).[28]

Signalling on the line is handled by Thales' SelTrac semi-automatic communication-based train control (CBTC) technology.[29]

As part of a contest organized by OC Transpo, each train set (on both the Confederation Line and the Trillium Line) was given a name that relates to local or Canadian history.[30]

An additional 38 Citadis Spirit vehicles were ordered by the city as part of the Stage 2 extension project with assembly beginning in early 2019.[31] Originally all 38 vehicles were to be assembled in Ottawa like the original order; however, in July 2019 Alstom announced it would move the assembly of the last 25 vehicles from this order to their new plant in Brampton.[32] As of July 2021, five of these vehicles had already been added to the operational revenue service fleet with several others in various stages of production and acceptance; most recent numbers also include 7 in line testing and 11 waiting for line testing. Each of the 38 additional vehicles will be added to the active Confederation Line fleet as they are completed.[33]

Vehicle issues

[edit]

The system encountered expected problems during testing with the train set during winter storms during early testing, including heating systems failing to work, communications systems failing, and body work on cars dropping off.[34]

Following the transition to full LRT service, in early October 2019 the automated doors of the Spirit vehicles experienced numerous faults if pried open or held back by passengers. This resulted in service disruptions lasting up to 90 minutes due to a lack of proper procedures to isolate and disable the faulty doors while a train was in service. The vehicles also began encountering integration issues with Thales' SelTrac train control system that would lead to the on-board computer for some trains in service needing to be rebooted, causing delays of up to 20–30 minutes.[35] Passengers also took issue with the overhead grab bars being too high to reach and that there were no straps to hold on to, with some resorting to scarves wrapped around bars or other means to stabilize themselves during travel.[36] OC Transpo subsequently ordered and installed straps on all trains. Because the original design of the vehicles did not include straps, RTG quoted the cost of procuring and installing them to be $1 million which OC Transpo rejected. OC Transpo said that by delaying the installation of the straps to after the line had launched, they only had to pay $200,000.[37]

Although vehicle reliability improved later into 2019, a series of new reliability issues began starting on December 31, 2019, when two trains failed due to electrical failures caused by improperly cleaned electrical contacts and led to disruptions that lasted several hours.[38][39] Throughout the start of 2020 the system's reliability issues continued with switch failures and continued unreliability of the vehicles. Insufficient heat generated by switch heaters would cause switches on the line to fail in heavy snowfall. Though the issue with the switch heaters had been flagged as a deficiency several times, the solutions implemented by RTG prior to the launch of the line were not effective at resolving the issue.[40] Issues with the vehicles ranged from electrical failures occurring in inclement weather caused by manufacturing defects in the inductors that feed power into the vehicles, to brake faults, and flat spots becoming a common occurrence on vehicles causing many to need to be taken out of service.[41] RTG struggled to keep up with the maintenance of the vehicles leading to several weeks where only a reduced number of trains could be operated during peak periods. On January 30, 2020, the Confederation Line reached an operational low when it was short five trains during rush hour due to "recurring mechanical and electrical issues".[42] The Confederation Line was expected to field 15 working trains during rush hour, although it only operated 13 vehicles at once during peak periods due to the system requiring more spares than originally thought. The city expected to be able to operate with 15 trains at peak by the end of August 2020 as additional vehicles were completed for Stage 2 and added to the fleet, and on August 7, 2020, 15 trains were launched for peak service without issue.[43][44]

Due to the unreliability of the system, the city has exercised its right to withhold the monthly maintenance payments it owes to RTG, which RTG disputes.[45] An exception was the payment for September 2019, which the city was contractually obligated to pay regardless of the service provided.[45]

Belfast Yard

[edit]

An ultimate capacity of 66 LRVs (most recent numbers show 57 LRVs having been delivered to the yard, 34 Stage 1, 5 Stage 2 joining the revenue service fleet, 7 Stage 2 in line test, 11 Stage 2 waiting for line testing, and the remaining 15 Stage 2 yet to be delivered) will be stored at the Belfast Yard at 805 Belfast Road, with connecting track to the Confederation Line; a further capacity up to 90 LRVs would be stored at the Moodie Yard. Part of the 6.5-hectare (16-acre) site was an existing OC Transpo facility. The yard site was created by combining this facility with the properties of a number of private business. All existing structures were demolished in 2013, and the new facilities were completed in 2016.[46] The facility has a storage shed, maintenance facilities and an administration office.[46] Final assembly for many of the LRVs was completed here.[46]

Accidents and incidents

[edit]
Repairs being done to the catenary system following a July 2022 lightning strike
  • August 8, 2021 – An empty train derailed while switching tracks after leaving Tunney's Pasture after one of the ten axles derailed. There were no injuries.[47][48] Technicians believe the derailment was caused by a loose connection of a wheel to its axle leading to excessive wear and eventual failure. An inspection of the fleet showed that nine other vehicles had the same problem.[49]
  • September 19, 2021 – A train with passengers derailed before entering Tremblay station after two axles became dislodged from the second car. After leaving Tremblay station in a derailed state, the train increased speed to about 35 kilometres per hour (22 mph), crossed a bridge over Riverside Drive, struck a signal mast and switch heater, and finally came to a stop between Tremblay station and Hurdman station using train-initiated emergency braking.[50] There were no injuries.[51][52] An improperly torqued bolt on the train's gearbox was identified as the cause of the derailment.[53] Service was partially resumed on November 12, 2021, with full service expected to resume by the end of November.[54][55]
  • July 24, 2022 – At approximately 11:15 pm, lightning struck the overhead catenary system, downing 900 metres (3,000 ft) of cable near Lees station. Train service between Rideau and St. Laurent stations was interrupted for four and a half days.[56][57]
  • July 17, 2023 – After an issue with an axle bearing on an LRV was discovered, the entire Confederation Line was shut down for nearly a month as the entire fleet underwent an emergency inspection.[58] Single car service returned to the line on August 14, 2023, with a supplementary shuttle service to handle additional traffic.[59]

Construction

[edit]
Demolition work at the Cyrville station (July 2015)

In mid-April 2015, OC Transpo posted a list of bus route changes as a result of the closure of the Transitway between Hurdman station and Blair station.[60] As a result of the closure, many new routes are being created, such as route 91, and existing routes modified, most notably routes 61, 62, 94 and 95. Many routes will use new bus-only lanes on Highway 417, and several others will be altered or shortened to avoid serving the construction area. The changes are meant to provide extra service to those in areas affected by the Transitway closure, and to avoid as many delays as possible while construction on the Confederation Line progresses. A side project on the 417 highway was completed in 2016.

Stage 2

[edit]
Stage 2 LRT logo

In November 2013, the City of Ottawa released its new transportation master plan,[61] which included plans to build 35 kilometres (22 mi) of new rapid transit and 19 new stations. This also included plans to extend the Confederation Line westward to Bayshore station and to Baseline station, and eastward to Place d'Orleans station. In July 2015, the city released a functional report on the Stage 2 system expansion,[62] which added plans to extend the Confederation Line eastward from Place d'Orleans station to Trim station. An extension westward to Moodie Drive from Bayshore station was announced in February 2017.[63] This totals an extension of 11 stations, 15 kilometres (9.3 mi) westward and 5 stations, 12 kilometres (7.5 mi) eastward.[64] Stage 2 will add a new light maintenance and storage facility along Corkstown Road, west of Moodie station.

Construction began in the second quarter of 2019, as the initial line became operational. While the expansion was initially expected to be complete by 2026,[65] the city stated in August 2024 that the full system could be operational by 2027, with the east extension to Trim operational by 2025.[66] Construction is currently ongoing, for implementation of the city's plan to address the current gap in service between Dominion station and Lincoln Fields station where buses travel on the Kichi Zibi Mikan a little over 4 kilometres (2.5 mi) without stopping.[67] The plan calls for burying trains for most of the route, creating a shorter, straighter alignment. The new route will also include two new LRT stations in an urban area with intensification opportunities.

See also

[edit]

References

[edit]

Inline citations

[edit]
  1. ^ Manconi, John (General Manager, Transportation Services) (January 23, 2020). Special Transit Commission meeting – January 23, 2020 (Audio Recording). 13 minutes in. Retrieved June 27, 2023.
  2. ^ "Line 1 opens on Sept. 14". octranspo.com. August 23, 2019. Archived from the original on August 23, 2019. Retrieved June 6, 2020.
  3. ^ "O-Train Line 1". www.octranspo.com. OC Transpo. Retrieved August 13, 2020.
  4. ^ "Transit commission on board with new O-Train name". Metro News. September 17, 2014. Archived from the original on February 9, 2018. Retrieved June 20, 2017. O-Train passengers could be boarding the expanded and newly named Trillium Line by mid-November
  5. ^ "Design, Build, Finance and Maintenance of Ottawa's Light Rail Transit (OLRT) Project" (PDF). Disposition 47. Ottawa City Council. December 19, 2012. [permanent dead link]
  6. ^ "2015 Look Ahead" (PDF). Confederation Line. 2015. Archived from the original (PDF) on September 25, 2015. Retrieved June 11, 2015.
  7. ^ a b Schepers (December 4, 2012), p.6
  8. ^ Chianello, Joanne (February 25, 2019). "4 things you should know about the $4.66B contract for LRT Stage 2". CBC News. Retrieved July 21, 2020.
  9. ^ Whan, Christopher (March 6, 2019). "Ottawa city council approves funding for stage 2 of LRT". Global News. Retrieved July 21, 2020.
  10. ^ Schepers (December 4, 2012), p.1
  11. ^ Pearson, Matthew (July 29, 2016). "LRT tunnel work under Rideau to resume next week". Ottawa Sun. Archived from the original on March 16, 2017. Retrieved March 15, 2017.
  12. ^ Pritchard, Trevor (December 22, 2016). "Rideau Street sinkhole collapse not city's fault, says chief solicitor". Canadian Broadcasting Corporation. Retrieved March 15, 2017.
  13. ^ Pearson, Matthew (December 16, 2017). "RTG unlikely to complete Confederation LRT Line by May 2018 deadline". Ottawa Citizen. Archived from the original on January 4, 2019. Retrieved July 21, 2020.
  14. ^ Willing, Jon (February 6, 2018). "City to open LRT by the end of November". Ottawa Citizen. Retrieved February 10, 2018.
  15. ^ "Ottawa, Alstom begin light rail testing on O-Train line". Trains Magazine. December 7, 2016. Retrieved December 7, 2016.
  16. ^ Slack, Jeff (May 10, 2019). "City still expects LRT handover end of June as Confederation Line construction wraps up". Ottawa Matters. Retrieved May 20, 2019.
  17. ^ Whan, Christopher (August 16, 2019). "Rideau Transit Group misses 4th deadline for LRT handover to City of Ottawa". Global News. Retrieved August 18, 2019.
  18. ^ "4 key dates as Ottawa's LRT becomes a reality". CBC. August 24, 2019. Retrieved August 26, 2019.
  19. ^ a b Pritchard, Trevor (March 13, 2020). "RTG 'misrepresented' its ability to build light rail, city says". CBC News. Retrieved March 13, 2020.
  20. ^ The Canadian Press (November 30, 2022). ""Egregious": Public inquiry finds "deliberate malfeasance" plagued Ottawa LRT project". Toronto Star.
  21. ^ a b "Confederation Line". City of Ottawa. 2015. Archived from the original on June 13, 2015. Retrieved June 11, 2015.
  22. ^ "Ready for Rail: How Often Will It Come? | Ottawa Confederation Line". www.ligneconfederationline.ca. Retrieved October 11, 2018.
  23. ^ a b c "Riding the LRT 101: What Ottawans need to know when the Confederation Line launches". Global News. March 20, 2019. Retrieved April 30, 2019.
  24. ^ Carlucci, Mario (October 25, 2019). "LRT stations slippery when wet, commuters complain". CBC News. Retrieved February 8, 2020.
  25. ^ "Project Agreement - Schedule 15-2 Part 1" (PDF). City of Ottawa.
  26. ^ "Alstom launches North American light rail vehicle with Ottawa contract". Railway Gazette International. February 14, 2013. Archived from the original on September 6, 2014. With a similar configuration to Citadis Dualis tram-trains used in the French cities of Nantes and Lyon, the version of the Citadis Spirit for Ottawa will be a 100% low-floor LRV with a top speed of 100 km/h and space for bicycles. It will be equipped to operate in 'extreme' winter conditions.
  27. ^ Vantuono, William (February 14, 2013). "Alstom finalizes Ottawa LRT contract". Railway Age. Retrieved June 20, 2017.
  28. ^ "How often will it come?". OC Transpo. Archived from the original on January 20, 2021.
  29. ^ "Ottawa LRT signalling award for Thales". Global Rail News. March 5, 2013. Archived from the original on April 10, 2013.
  30. ^ "Take the 'Eh-Train': Ottawa reveals names of 40 LRT cars". CBC. Retrieved October 11, 2018.
  31. ^ "Report to: Council" (PDF). February 22, 2019. Retrieved February 25, 2019.
  32. ^ Chianello, Joanne (July 6, 2019). "Finishing LRT trains by Sunday 'entirely achievable,' rail director says". CBC. Retrieved September 21, 2019.
  33. ^ "Transit Service Recovery Plan Update" (PDF). June 17, 2020.
  34. ^ "'Unreliable' LRT trains can't handle Ottawa winters, internal reports reveal". CBC News.
  35. ^ Spurr, Ben (October 12, 2019). "Metrolinx not concerned about Ottawa LRT issues, despite having order in for the same vehicles". Toronto Star. Retrieved October 12, 2019.
  36. ^ "LRT riders looking for something to hold on to". CBC News Ottawa. December 1, 2019. Retrieved October 1, 2024.
  37. ^ Porter, Kate (December 18, 2019). "Straps coming to all LRT trains by end of January". CBC News. Retrieved February 7, 2020.
  38. ^ Porter Kate 2020, CBC News https://www.cbc.ca/news/canada/ottawa/lrt-nye-2019-dirt-electrical-1.5412962)
  39. ^ (Spears Tom 2020, https://ottawacitizen.com/news/local-news/lrt-outage-slows-travel-for-new-years-eve-party-crowds)
  40. ^ "City inspectors noted problems with LRT switch heaters over two winters, flagged serious deficiencies in lead up to March deadline". Ottawa Citizen. Retrieved June 6, 2020.
  41. ^ "RTG tries to make headway on recurring LRT problems but jolted by one-off mishaps". Ottawa Citizen. Retrieved June 6, 2020.
  42. ^ (Brietnef, Beatrice 2020, https://globalnews.ca/news/6483978/ottawas-lrt-short-5-trains-thursday-as-electrical-wheel-issues-continue/)
  43. ^ "City outlines issues to fix Confederation Line, wants 15 trains by Aug. 4". Ottawa. March 13, 2020. Retrieved June 6, 2020.
  44. ^ "LRT runs with 15 trains for the first time". CTV News Ottawa. August 7, 2020. Retrieved August 9, 2020.
  45. ^ a b Raymond, Ted (February 10, 2020). "Mayor calls for regular updates on payments to RTG after confusion over September cheque". Ottawa. Retrieved June 6, 2020.
  46. ^ a b c https://www.ligneconfederationline.ca/the-build/maintenance-facility/overview/ [bare URL]
  47. ^ "LRT wheel derailed while switching tracks: TSB". August 9, 2021. Archived from the original on August 9, 2021.
  48. ^ "LRT service to remain suspended until the weekend following minor derailment". CTV News. August 10, 2021. Retrieved September 19, 2021.
  49. ^ "Why the bumpy, two-year ride of Ottawa's multibillion-dollar LRT system is sparking calls for a public inquiry". Toronto Star. September 26, 2021.
  50. ^ "Rail transportation safety investigation R21H0121 - Main-track train derailment". Transportation Safety Board of Canada. October 6, 2021. Retrieved October 10, 2021.
  51. ^ "LRT shut down again after 2nd train derailment since August". Archived from the original on September 19, 2021.
  52. ^ "LRT train derails on Confederation Line near Tremblay Station". CTV News. September 19, 2021. Retrieved September 19, 2021.
  53. ^ "'Workmanship,' loose bolts blamed for Ottawa LRT derailment – Ottawa". Global News. Retrieved October 27, 2021.
  54. ^ "Return-to-service testing begins on Ottawa's LRT five weeks after derailment". CTV News. October 27, 2021. Retrieved October 27, 2021.
  55. ^ "Ottawa LRT expected to resume partial service Friday". CBC News. November 9, 2021. Retrieved November 9, 2021.
  56. ^ Kupfer, Matthew (August 24, 2022). "Video shows lightning strike damage that stopped LRT service in July". CBC Ottawa. Retrieved September 20, 2022.
  57. ^ Pringle, Josh (July 29, 2022). "Ottawa LRT system resumes full service after lightning strike". CTV News Ottawa. Retrieved September 20, 2022.
  58. ^ "Here's what you need to know about the O-Train shutdown and R1 service today". Ottawa. July 21, 2023. Retrieved July 21, 2023.
  59. ^ Pringle, Josh (August 14, 2023). "OC Transpo gives the green light for full O-Train service to resume on Monday". CTV. Retrieved August 14, 2023.
  60. ^ "OC Transpo – On Track 2018". April 2015. Retrieved April 19, 2015.
  61. ^ "Transportation Master Plan". City of Ottawa. Archived from the original on August 10, 2015. Retrieved March 2, 2015.
  62. ^ City of Ottawa (June 29, 2015). "Stage 2 LRT". Stage 2 LRT Resources. City of Ottawa. Archived from the original on July 8, 2015. Retrieved July 6, 2015.
  63. ^ Willing, Jon (February 17, 2017). "'The west is finally in': $3.6B rail package includes LRT to Moodie Drive". Ottawa Citizen. Retrieved August 19, 2017.
  64. ^ "Stage 2 – East, West and South". City of Ottawa. 2015. Retrieved August 1, 2015.
  65. ^ Porter, Kate. "Western Stage 2 LRT construction now 17 months behind". CBC News. Retrieved November 3, 2022.
  66. ^ Glass, Marlo. "Ottawa LRT west extension could be ready for passengers by 2027, city says". Ottawa Citizen. Retrieved August 3, 2024.
  67. ^ "Unsatisfied with City proposal partially bury western extension". Ottawa Citizen. Archived from the original on June 19, 2013. Retrieved June 12, 2013.

Bibliography

[edit]
[edit]

45°25′09″N 75°40′45″W / 45.41905°N 75.67906°W / 45.41905; -75.67906